Highlight the start of collection and assembly of several corresponding to the metal structure which integrates the compression ring of the general cover modules.
the assembly work stands the three grandstands, high, medium and low have been completed, the absence of the stands of low position stands coincident with tower cranes.
Continue units for the execution of different types of flooring, waterproofing wet areas and terraces on various levels, based divisions block factory work, and drywall work level 1 start, bound -11.20 / - 9.54.
Sand blasting Peineta bleachers as part of the rehabilitation of this structure is continued.