Work continues foundation either in their piloting in southwest and northeast areas, pile caps of south and west of the area under eaves comb.
Anchoring Screen southern arm is complete, and has continued with the emptying of land annexed to screen for preparing the working platform of the following piles run in south zone.
Continuing the implementation of walls, columns, and slabs on north, towards this area, parallel to these works sanitation pits and lands network are executed.