Closed rings post-tensioned slabs and armed levels 2 and 3, both in northwest; good progress implementing environmental portagradas beams stands, having started in the same south, and continuing with the implementation of slabs level 4, level zero; parallel working to close ring slabs cantilevered middle stands between northern areas and low comb.
Continues waterproofing and drainage extrados wall in south.
In northern elevation has been reached for the exterior foundation walls, deep pile based CPI-6, which will start shortly foundation.
Inside the comb working on closing the structural joints, selective demolition for new stairs, and connections with new slabs.