Throughout the month of May there have been significant advances in different work units.
You have completed the assembly stands high stands; They have begun the rehabilitation of bleachers Peineta by applying sandblast for surface devastated.
execution pending formation corresponding to the terraces of the elevation +8.40 m trafficable flat roofs starts., terraces and facilities +12.25 m height.
Continues execution of divisions based factory block, execution of concrete flooring surface treatment levels -11.20 m and -9.54 m., and continues assembling facilities.
With respect to the structure, indicate that advances in the various stages of concreting battery general support deck.